| Route 18 improvements won’t be done piecemeal
By JACK ENCARNACAO
The Patriot Ledger
WEYMOUTH - A Route 18 improvement project got a boost when the state Highway
Department announced that work on three intersections will be done
simultaneously by one contractor.
Some people anticipated that the intersections would be worked on one by one,
but state highway officials were able to lump them together, which likely means
the work will be finished sooner.
‘‘You can centralize work and effort and manpower on the projects themselves
because they are combined into one,’’ Erik Abell, spokesman for the state’s
Executive Office of Transportation, said yesterday.
The improvements include widening Route 18 and rebuilding the intersections
at Middle, Park and Columbian streets.
The work will be advertised to contractors until late August. After bids have
been submitted, a company will be selected to do the work, some of which is
expected to take place in the fall, Abell said. The work is to be completed by
November of 2008.
The work is important to redevelopment of the South Weymouth Naval Air
Station because the state requires completion of the project before homes and
businesses can be built on the former base.
A widened Route 18 and improved intersections will also help carry the
thousands of vehicles expected to travel to and from the redeveloped 1,405-acre
base each day.
Terry Fancher, executive director of the base overseer, Tri-Town Development
Corp., said the state Highway Department’s announcement is ‘‘excellent news.’’
‘‘It’s one that we’ve been holding our breaths on,’’ he said. ‘‘We’ve been
pushing for a while to keep those intersections as a package. It seems to make
sense... If you can have them as a package deal, it will get the job done a
little bit quicker than it might have before.’’
The Pond Street-Pleasant Street intersection project, completed recently,
took far longer than expected. Utility companies and the Highway Department
could not coordinate with each other, and workers were unable to finish final
phases of the project until utility companies moved their poles and wires.
‘‘It went on for two full construction seasons. There’s no way that we can go
through that agony again,’’ said town council member Michael Smart, whose
district includes the Route 18 area. ‘‘They certainly need to do a better job
coordinating it. Those things need to be ironed out prior (to work starting).’’
Base developer LNR Property Corp. is working with utility companies to ensure
that relocation of utility poles and other equipment takes place in a timely
manner along with the intersection improvements.
Asked in May about the utility snafus on the first job, Highway Department
spokesman Jon Carlisle said, ‘‘Unfortunately, utility work is something that
does become an issue from time to time, largely because it’s out of our control.
You have to deal with utilities when you do something like this.’’
One of the first steps in the new intersection projects is land taking: state
purchasing of driveways, curbs and any other slivers of land that will be paved
over when streets are widened.
By the time the four intersections have been completed, the state will have
acquired 209 parcels of land along Route 18 to allow the improvements.
Jack Encarnacao may be reached at
jencarnacao@ledger.com .
Copyright 2006 The Patriot Ledger
Transmitted Wednesday, July 12, 2006
|